What is the procedure to file a complaint under RERA 2016 against a builder who has delayed possession of my flat? What are the possible defenses someone can use in this situation?

AS Asked by Ashwini Dasgupta from India

Quick Answer

To file a complaint under the Real Estate (Regulation and Development) Act, 2016 (RERA 2016) against a builder for delayed possession of your flat, you need to follow a systematic procedure as outlined in the Act. Here are the steps to file a complaint:Gather Documentation: Collect all relevant documents such as the sale agreement, payment receipts, and any correspondence with the builder regardin

Detailed Legal Analysis

To file a complaint under the Real Estate (Regulation and Development) Act, 2016 (RERA 2016) against a builder for delayed possession of your flat, you need to follow a systematic procedure as outlined in the Act.

Here are the steps to file a complaint:

  • Gather Documentation: Collect all relevant documents such as the sale agreement, payment receipts, and any correspondence with the builder regarding possession.
  • Check RERA Registration: Ensure that the builder is registered under RERA by checking the official RERA website for your state.
  • File Complaint with RERA Authority: Draft a formal complaint detailing the issue and submit it to the appropriate RERA authority in your state, along with the required documents.
  • Pay Filing Fees: Pay the prescribed filing fee, which varies by state, as part of the complaint submission process.
  • Attend Hearings: After filing, you may be called for a hearing. Be prepared to present your case and any evidence you have.
  • Await Judgment: The RERA authority will issue a judgment based on the evidence presented. This may include orders for possession, compensation, or penalties against the builder.

As per Section 18 of RERA 2016, if the builder delays possession, the buyer is entitled to compensation, which may include a refund of the amount paid with interest, or possession of the flat along with interest for the delay period.

Possible defenses that a builder might use in such situations include:

  • Force Majeure: Claiming that unforeseen circumstances like natural disasters, labor strikes, or government regulations have prevented timely completion.
  • Buyer’s Delay: Arguing that the buyer delayed in making payments or fulfilling their obligations under the sale agreement.
  • Change in Project Plans: Asserting that changes in project design or approvals from authorities caused delays, which were communicated to buyers.
  • Contractual Clause: Referring to specific clauses in the sale agreement that allow for delays under certain conditions.

It is advisable to consult with a legal professional specializing in real estate to ensure that your complaint is well-founded and to navigate the complexities of the RERA process effectively.

Legal Provisions Referenced

Transfer of Property Act 1882, Land Acquisition, and relevant provisions of Indian law

Verify the current statutory text at India Code (the official repository of Indian legislation) or the Legislative Department. This answer is general legal information, not advice on your specific matter.

Last updated: August 3, 2026 AI-assisted answer

Disclaimer: AI-generated for educational purposes only. Does not constitute legal advice. Consult a qualified practitioner.

This explains property law law in general. Your own matter has its own facts.